Template

Risk Register Template

Capture project risks, causes, impacts, probability, response actions, owners, due dates, and escalation status.

Use this template to manage risk before it becomes an issue

The risk register provides one controlled place to track risk exposure, mitigation actions, ownership, review dates, and escalation status.

Its value depends on regular review, clear ownership, and timely action.

Template fields

Risk ID

Unique reference number.

Risk Title

Short name summarizing the risk.

Risk Description

Clear description of the uncertain event or condition.

Cause

The reason the risk may occur.

Impact

The effect on the project if the risk occurs.

Impact Area

Scope, schedule, cost, quality, safety, contract, stakeholders, resources, benefits, or reputation.

Probability

Likelihood that the risk will occur.

Impact Rating

Severity of the effect if the risk occurs.

Risk Score

Combined view of probability and impact.

Risk Level

Low, medium, high, or critical.

Risk Owner

Person accountable for monitoring the risk and ensuring response actions are completed.

Response Strategy

Avoid, mitigate, transfer, accept, or escalate.

Mitigation Actions

Actions agreed to reduce probability or impact.

Action Owner

Person responsible for completing the mitigation action.

Due Date

Target date for completing the action.

Status

Open, in progress, monitoring, escalated, or closed.

Escalation Required

Yes or no, with escalation level if needed.

Review Date

Next date when the risk should be reviewed.

Recommended risk review process

  1. Identify new risks.
  2. Validate existing risks.
  3. Update probability and impact.
  4. Review mitigation actions.
  5. Confirm owners and due dates.
  6. Escalate risks outside project tolerance.
  7. Close risks that are no longer relevant.
  8. Report major risks through governance forums.

Good risk statement format

Recommended structure: Because of [cause], there is a risk that [risk event], which may result in [impact].

Example: Because design approvals are delayed, there is a risk that procurement will start late, which may result in schedule delay and increased delivery cost.

Common mistakes

  • Listing issues as risks
  • Writing vague risk descriptions
  • Not assigning risk owners
  • Using the risk register only for reporting
  • Not escalating high risks
  • Closing risks without evidence
  • Ignoring schedule, cost, and contractual impacts

Related PM Hub resources